Able Demolition v. Pontiac May 17th, 2007

Here’s the case.

— Read for your self below before reading my opinion and making your comments. Please come to the table with your opinion which is unbiased. (Copied from https://caselaw.findlaw.com/mi-court-of-appeals/1467265.html )

Before:  SMOLENSKI, P.J., and SAAD and WILDER, JJ. Penzien & Associates, PLLC (by Charles M. Penzien), Mount Clemens, for the plaintiff. Bigler, Berry, Johnston, Sztykiel & Hunt, P.C. (by Eric S. Goldstein and Mary Jo Boerman), Zeeland, for the defendant.

Able Demolition, Inc., appeals the trial court’s grant of summary disposition to the city of Pontiac.   For the reasons set forth below, we affirm the trial court’s ruling.

I. Facts and Procedural History

On July 1, 2004, Able Demolition contracted with Pontiac to tear down certain abandoned homes.   As the below-quoted provisions of the contract make clear, Able was required to obtain specific written permission to proceed before demolishing any building:

IV. SCOPE OF SERVICES

4.01 The Contractor shall diligently perform certain Demolition Services for the City of Pontiac, primarily for the Department of Community Development, as outlined in the attached “Contract Documents.”   The term “Contract Documents” means and includes the following:  1) Performance Bond;  2) Bid Tally Sheet;  3) Specifications (including any supplemental specifications and special provisions.)

4.02 The demolition services shall be performed over the course of the one (1) year contract, and shall include, but not be limited to, work as specified on the Purchase Order attached hereto, incorporated hereto marked as Exhibit “A” regarding _,

(address of building)

4.03 The Contractor is an independent contractor and shall not be subject to the specific direction or supervisions of any representative of the City, except in regard to the determination of the acceptability of the Contractor’s work product by the Director of the Community Development Department and the Mayor of the City of Pontiac, and in regard to the mandatory requirements that the Contractor get pre-demolition authorization (“Letter to Proceed” described below) from the Director of Law or their designees prior to performance and/or demolition.

* * *

V. PRE-DEMOLITION APPROVAL

5.01 Prior to any performance of services by the Contractor under the terms of this contract and pursuant to a successful bid, the Contractor must, on the date that the anticipated services will be performed (mandatory), contact the Director of Law or their designee to secure written approval to proceed with said services.   Upon request for approval by the Contractor, the Director of Law or their designee will provide said Contractor with a “Letter to Proceed” which will specifically grant the Contractor written approval to proceed with said specified services.   Prior to any payment under the terms of this contract (Section VI. Compensation), the Contractor must present the “Letter to Proceed” (Director of Law’s-City Attorney’s approval documentation) to the Director of Finance of the City verifying that approval to proceed was granted.   If the Contractor proceeds without the approval specifically granted in the “Letter to Proceed”, the Contractor shall forfeit any payment for unauthorized services performed as a result of his failure to get said pre-approval “Letter to Proceed”.

* * *

VII. COMPENSATION

7.01 The City agrees to pay the Contractor for the Demolition Services performed pursuant to Paragraph 4.02 in the amount of —- Thousand —-Hundred and —-/100 Dollars ($ —-.—-),  itemization required), not to exceed a maximum of One Hundred Thousand and 00/100 Dollars ($100,000.00) for the entire one (1) year contract.   If the “Letter to Proceed” for each demolished property is not provided, the Contractor forfeits any payment under the terms of this contract.

* * *

VIII. METHOD OF PAYMENT

8.01 Contractor shall submit monthly “Itemization Statements” for services along with the “Letters to Proceed” in accordance with the provisions of this Contract.   The original of said “Itemization Statement and “letters [sic] to Proceed” must be sent to the Director of the Community Development Department.   Copies must also be provided to the Finance Director and to the Director of Law and the City of Pontiac.

Able maintains that it demolished numerous buildings under the contract, but that Pontiac refused to pay $42,299 for 11 of the demolitions that Able completed.   Able filed a complaint against Pontiac on May 10, 2006, and alleged claims of breach of contract, promissory estoppel, unjust enrichment, and quantum meruit.

In lieu of an answer, Pontiac filed a motion for summary disposition under MCR 2.116(C)(10), and argued that Able is not entitled to payment because it did not comply with the material terms of the contract.   Specifically, Pontiac asserted that Able failed to obtain letters to proceed as required by § 5.01 for 11 of the houses it demolished and that, therefore, Able forfeited its right to payment for those demolitions.   In response, Able asserted that it substantially performed under the contract and it did not materially breach the agreement when it failed to obtain letters to proceed.   Following oral argument, the trial court ruled that the contract language clearly and explicitly states that a letter to proceed is required before Able performs a demolition and before Able is entitled to payment.   For that reason, the trial court granted summary disposition to Pontiac.

II. Analysis

A. Standard of Review

This Court explained in Hamade v. Sunoco Inc. (R & M), 271 Mich.App. 145, 165-166, 721 N.W.2d 233 (2006):

This Court ․ reviews de novo the proper interpretation of a contract.   Clark v. DaimlerChrysler Corp., 268 Mich.App. 138, 141, 706 N.W.2d 471 (2005).   Likewise, whether a contract’s terms are ambiguous is a question of law this Court reviews de novo.  Wilkie v. Auto-Owners Ins. Co., 469 Mich. 41, 47, 664 N.W.2d 776 (2003).   When a contract is unambiguous, it must be enforced according to its terms.  DaimlerChrysler Corp. v. G-Tech Professional Staffing, Inc., 260 Mich.App. 183, 185, 678 N.W.2d 647 (2003).[[1]

B. Contract Interpretation

Section 5.01 of Able’s contract with Pontiac unambiguously requires that, on the day of each demolition, Able must obtain written assurance from Pontiac’s director of law before Able may go forward with the destruction of a building.   Sections 5.01, 7.01, and 8.01 also plainly state that, to be paid, Able must submit the letters to proceed to the city and various city representatives.   The contract also provides that, if a contractor fails to submit the letters, the company forfeits its right to payment.

 As our Supreme Court explained in Quality Products Concepts Co. v. Nagel Precision, Inc., 469 Mich. 362, 375, 666 N.W.2d 251 (2003):

In interpreting a contract, our obligation is to determine the intent of the contracting parties.  Sobczak v. Kotwicki, 347 Mich. 242, 249, 79 N.W.2d 471 (1956).   If the language of the contract is unambiguous, we construe and enforce the contract as written.  Farm Bureau Mut. Ins. Co. of Michigan v. Nikkel, 460 Mich. 558, 570, 596 N.W.2d 915 (1999).   Thus, an unambiguous contractual provision is reflective of the parties’ intent as a matter of law.   Once discerned, the intent of the parties will be enforced unless it is contrary to public policy.  Id.

Here, the language of the contract is clear:  the contractor, Able Demolition, must obtain a letter to proceed from the city’s legal department before it can proceed.2  The question here is what is the legal consequence of the contractor’s failure to comply with this unambiguous contractual obligation.

C. Condition Precedent 3

 Because the contractual language is clear, we need not interpret this contract.   Instead, we address the question of the legal consequences of plaintiff’s failure to comply with its straightforward obligation.   We hold that the contract provision that required Able to obtain letters to proceed is a condition precedent and that Able’s failure to comply with this provision means that it was not entitled to performance by Pontiac, i.e., payment for demolition services.   A condition precedent ‘is a fact or event that the parties intend must take place before there is a right to performance.’  Mikonczyk v. Detroit Newspapers, Inc., 238 Mich.App. 347, 350, 605 N.W.2d 360 (1999), quoting Reed v. Citizens Ins. Co. of America, 198 Mich.App. 443, 447, 499 N.W.2d 22 (1993).  “Failure to satisfy a condition precedent prevents a cause of action for failure of performance.”  Berkel Co. Contractors v. Christman Co., 210 Mich.App. 416, 420, 533 N.W.2d 838 (1995).

  “ ‘Courts are not inclined to construe stipulations of a contract as conditions precedent unless compelled by the language in the contract.’   Mikonczyk, supra at 350, 605 N.W.2d 360, quoting Reed, supra at 447, 499 N.W.2d 22.   The clear and unambiguous language of the disputed provision compels the conclusion that the parties intended that Able must obtain a letter to proceed before each demolition, in order to trigger its right to payment.   Section 4.03 of the contract states that prior to performance and/or demolition,” Able must “get pre-demolition authorization,” and 5.03 specifies that “Prior to any performance of services ․ [Able] must, on the date that the anticipated services will be performed (mandatory), contact the Director of Law or their designees to secure written approval to proceed with said services.”  (First and second emphasis in original;  third emphasis added.)   Moreover, § 7.01 unequivocally states that “[i]f the ‘Letter to Proceed’ for each demolished property is not provided, [Able] forfeits any payment under the terms of this contract.”   Again, the contract repeatedly states that Able’s right to payment is contingent on its acquiring and submitting the letters, and this did not occur.   In other words, the contractual language unambiguously sets forth the condition, clarifies its importance, and states the consequences of a failure to comply with the condition.   Able acknowledges that it failed to obtain the letters, and, because of this failure, Pontiac is not obligated to perform under the contract.   Accordingly, the trial court correctly granted summary disposition to Pontiac.

D. Substantial Breach

 Were we to conclude that the letter to proceed provision constitutes a duty or a promise rather than a condition precedent, Able would not be entitled to recover under the contract.   Again, Able concedes that it failed to comply with the terms of the agreement when it failed to obtain preapproval letters before it demolished the buildings for which it now seeks compensation.  ‘The rule in Michigan is that one who first breaches a contract cannot maintain an action against the other contracting party for his subsequent breach or failure to perform.’  Michaels v. Amway Corp., 206 Mich.App. 644, 650, 522 N.W.2d 703 (1994), quoting Flamm v. Scherer, 40 Mich.App. 1, 8-9, 198 N.W.2d 702 (1972).   However, the rule only applies if the initial breach was substantial.  Id.  To determine whether a substantial breach occurred, a trial court considers “whether the nonbreaching party obtained the benefit which he or she reasonably expected to receive.”   Holtzlander v. Brownell, 182 Mich.App. 716, 722, 453 N.W.2d 295 (1990).   Able maintains that it demolished buildings, which was the central purpose of the agreement, and that, therefore, its failure to obtain and submit the preapproval letters should not excuse Pontiac’s obligation to pay for its services.

 We disagree with Able’s assertion for several reasons.   Though the contract contemplated that Able would perform demolition services for the city, the contract here is more than a mere services contract.   Rather, the contract is a “legal protocol,” and, as such, the critical aspect of the agreement is that any demolition be accomplished in strict compliance with the procedures designated by Pontiac’s legal department to minimize the risk of legal liability and the serious violation of citizens’ property rights.   A demolition company must ask the city for a letter on the day of each demolition because, in some cases, a property owner may obtain a last-minute temporary restraining order to prevent destruction of a building.   Clearly, the city insists on the clause to avoid liability for demolitions that should not, legally, go forward.   This intent is clear because the contract language makes the letter to proceed mandatory on the date the demolition is performed, and this preapproval letter must be issued by the city’s director of law.   Because this step is in the contract to protect property rights and to protect the city from exposure to liability, the letter-to-proceed provision is an essential term of the contract and not a mere technicality.   Indeed, the term goes to the heart of the agreement and reflects that the parties understood that the underlying action-the demolition of property-carries with it serious legal implications for all parties.   If the parties were not bound by this term, the legal safeguards set forth in the agreement would be rendered meaningless.   Thus, we hold that Able’s breach was substantial and that Able may not maintain an action for damages against Pontiac as a matter of law.4

Affirmed.

I agree with and join in parts I and II(A), (B), and (C) of the majority opinion.

FOOTNOTES

1.   The trial court granted summary disposition to Pontiac under MCR 2.116(C)(10).  “This Court reviews the grant or denial of summary disposition de novo to determine if the moving party is entitled to judgment as a matter of law.”  Maiden v. Rozwood, 461 Mich. 109, 118, 597 N.W.2d 817 (1999).   As the Maiden Court further explained:A motion under MCR 2.116(C)(10) tests the factual sufficiency of the complaint.   In evaluating a motion for summary disposition brought under this subsection, a trial court considers affidavits, pleadings, depositions, admissions, and other evidence submitted by the parties, MCR 2.116(G)(5), in the light most favorable to the party opposing the motion.   Where the proffered evidence fails to establish a genuine issue regarding any material fact, the moving party is entitled to judgment as a matter of law.  MCR 2.116(C)(10), (G)(4).  Quinto v. Cross Peters Co., 451 Mich. 358, 547 N.W.2d 314 (1996).  [Maiden, supra at 120, 597 N.W.2d 817.]

2.   For the first time on appeal, Able avers that the contract language is ambiguous.   Able did not assert in the trial court that the contract is unclear and, therefore, this issue is not preserved for appeal.  Fast Air, Inc. v. Knight, 235 Mich.App. 541, 549, 599 N.W.2d 489 (1999).   Nonetheless, Able’s claim lacks merit.   Section 5.01 provides that, if the demolition contractor fails to obtain a letter to proceed, it forfeits any payment for unauthorized services.   Able contends that the phrase unauthorized services is ambiguous because, with further discovery, Able may be able to show that Pontiac officials authorized the demolitions and, therefore, the demolitions would not amount to an unauthorized service under the contract.   First, that other officials may have authorized Able to demolish certain buildings does not render the contract language ambiguous.   Further, the remainder of the section states that the failure to obtain letters to proceed constitutes a forfeiture of payment for unauthorized services performed as a result of his failure to get said pre-approval ‘Letter to Proceed.’   A plain reading of the section compels the conclusion that unauthorized services refers directly to the failure to obtain letters to proceed.   Accordingly, that Able may have obtained permission from another source does not render the contract ambiguous and does not excuse performance under the terms specified in the agreement.

3.   The Restatement of Contracts now refers to a “condition precedent” simply as a “condition.”  Restatement Contracts, 2d, § 224, comment e, p. 163.   Here, we use the term “condition precedent” because it most aptly describes the precondition at issue and because our courts have continued to use the term since the Restatement’s change.

4.   To the extent Able continues to maintain its unjust enrichment, quantum meruit, and promissory estoppel claims, we affirm their dismissal.   A claim of unjust enrichment does not apply if there is an express contract, Martin v. East Lansing School Dist., 193 Mich.App. 166, 177, 483 N.W.2d 656 (1992), and the same is true for a quantum meruit claim.   Dykema Gossett PLLC v. Ajluni, 273 Mich.App. 1, 8-9, 730 N.W.2d 29 (2006).   Furthermore, the contract contains an integration clause;  therefore, it would have been unreasonable as a matter of law for Able to rely on any outside representations to support a promissory estoppel claim.  UAW-GM Human Resource Ctr. v. KSL Recreation Corp., 228 Mich.App. 486, 504, 579 N.W.2d 411 (1998).

SAAD, J.

SMOLENSKI, J., concurred.

I Agree with the Ruling

The contract was very specific and clear on the obligations or parameters that Able’s Demolition needed to exercise before beginning work and to receive compensation for their work. Whenever a contract is signed, all the information within the contract is relevant (as long as it is not- “voidable or unlawful or isn’t unconscionable” (Brown & Sukys, 2020, Chapter 7& 8 ) Yes, if this part of the contract was boiler plate text, then I could see how it could be unconsidered (Kar & Raddin, 2019. Para. 16). Clearly, these sections in regards to commencement and payment were explicit not boilerplate.

The phrase, “Checking all the boxes,” refers to meeting all the requirements (Amlen, 2019).

The City of Pontiac did not breach their contract with Able, yet Able did first and materially breach the contract. The reason that the City included the following requirements in the contract was for public safety.

The City of Pontiac’s Express Requirements to Commence Work and for Payment

  • Contractor must (Section V Pre-Demolition Approval),
    • Secure written approval to proceed
    • On the anticipated date of service,
    • From the Director of Law or Designee, and
    • Secure a “Letter to Proceed.”
  • Contractor must,
    • Present the “Letter to Proceed”
    • To the Director of Finance of the City, and
    • Before executing services.
  • Otherwise it is an unauthorized service and forfeit any payment (Section V & Section VII. Compensation).

Able’s Demolition argues that the contract was ambiguous, that the City breached the contract, promissory estoppel, unjust enrichment and quantum meruit.

Able’s Arguments Against the City and Why Their Arguments Did Not Stand Up in Court.

  • Able breached the contract substantially, not the City. The City did everything is said it would do if Able did not secure and present the letter to proceed before commencing work. Also, even if Able could show breach of contract, they in fact were the first party to breach the contract. Additionally, by the City not paying Able, they are indeed doing what they said they would do within the language of the contract. They are actually upholding the contract. If they would have paid Able, then they would have been breaking the contract.
  • Able claims the contract was ambiguous. The contract was in-fact explicit.
  • Able says the City is benefiting from unjust enrichment. However, these rules and conditions are put into place to protect the public, and private citizens from their property being destroyed. Such that at the last minute, a person can obtain a temporary re-straining order to stop the demolition. These checks and balances are put into place to protect the rights of the citizens. Thus, the City is not hoping to unfairly gain financially, yet keep the strict policy secure in order to protect people’s property.
  • Able claims promissory estoppel , which would protect them in the case of this breach, because they relied upon the payment promise, then suffered a loss by not getting paid. This does not stand up in court, because the clauses in quest are condition precedent. Able’s had explicit conditions required before acting and getting paid.
  • Able claims quantum meruit or that they have earned the money owed to them for their services. All of the above reason’s disproved this allegation. It was because the clauses are condition precedents.
  • Additionally, Able breached the contract first, thus they can not pursue action. Additionally, by the City not paying Able, they are indeed doing what they said they would do within the language of the contract. They are actually upholding the contract. If they would have paid Able, then they would have been breaking the contract.

Discussion and Opinion

Able may have not understood the gravity of these conditions and the possible consequences. They may have been more familiar with working with private contracts versus public contracts. They have been loose on these types of conditions of the contract in the past and not suffered. They may have truly thought unjust enrichment, promissory estoppel and quatem meruit would protect them by proceeding with work without the explicit conditions from the “Letter to Proceed”. It is also possible that there is a lack of communication on its way down the chain of command. Slipping through the cracks because of poor communication or checks and balances is no excuse. Particularly for a service that has un-reversible actions that can severely do damage to other people’s property.

A material breach is one that explicitly states that something specific will make the contract invalid or void. Basically, it invalidates the breaching parties right to sue. The entire section in regards to the “letter to proceed” requirement was a material breach of contract. When Equifax data was breached in 2017, a class action lawsuit stated that the forty day waiting period to disclose this to shareholders and clients was a material breach of contract (Bottum, 2019, Pg. 2099). The SEC has a four day period after discovery of a data breach to disclose the breach (Bottum, 2019, Pg. 2126). Thus a material breach of contract according to SEC regulations. During this month and a half delay Equifax sold about $2 million in shares, which investors may not have done knowing this new information.

There are protections against breaches when services are provided and costs incurred, and the other party benefits. That is the unjust enrichment protection. However, the City made it clear that the protection of the rights of citizens and their private property was their priority, not gaining a service at no cost.

For an unjust enrichment claim, there must be an ‘unjust factor’

(Jaffey, 2014, Pg. 987, Para. 3)

Also, out of the box language or boilerplate text can be omitted. Why? Boilerplate text can be omitted as part of the actual terms of a contract because there is not a shared meaning. “The shared meaning of a contract or the (‘common meaning of the parties’) as that meaning that is most consistent with the presupposition that both parties were using language cooperatively to contract” (Kar & Radin, 2019. Para. 3). As anyone can see, the parts of the contract called into question are not generic, yet very explicit.

Contractors deal in contracts; it is in the name of their profession, ‘Contractors.’ I’m not a contractor and do not deal in formal contracts with this much consideration on a regular basis. As a person unfamiliar with this type of work, and if I were presented with this contract before starting a business relationship, especially for the amount of money and costs at stake, this section would make me pause and clarify.

Nether the less, if anyone signs a contract that expressly and specifically spells out requirements, take care to check the boxes and plan them into execution.

References

Amlen, D. (June 26, 2019). Fulfill Requirements. Retrieved from https://www.nytimes.com/2019/06/26/crosswords/daily-puzzle-2019-06-27.html on November 11th, 2019

Bottum, T. (2019). Material breach, material disclosure. Minnesota Law Review, 103(4), 2095.

Gordon, B. & Sukys, P. (2020).  Business Law with UCC Applications. 15th ed., 2020.

Jaffey, P. (2014). Unjust Enrichment and Contract. Modern Law Review, 77(6), 983–993. https://doi-org.proxy.davenport.edu/10.1111/1468-2230.12099